LRPC Strand for Precast: A Repeat-Order Planning Guide

Buying LRPC strand for precast production involves more than checking the price of the next coil. Each purchase needs to match the approved specification, the production schedule and the material already available at the yard.

A repeat-order plan helps purchasing, production and quality teams work from the same information. Before requesting a quotation, establish what material is required, how much usable stock remains and when the next delivery needs to arrive.

Wire Shoppe P Ltd supplies Tata make LRPC strand from Nagpur across India. This guide outlines the information buyers can prepare before placing a first or repeat order.

1. Start with the approved strand specification

Use the specification approved for the precast element or project as the starting point for procurement. A previous purchase order can be a useful reference, but confirm that its requirements still apply to the next production run.

Wire Shoppe’s listed Tata LRPC strand sizes include:

Listed Tata LRPC strand specifications
Specification12.9 mm LRPC strand15.2 mm LRPC strand
Nominal cross-sectional area100 mm²139 mm²
Nominal unit weight781 g/m1,086 g/m
Minimum breaking load186 kN259 kN
Nominal tensile strength1,860 MPa1,860 MPa
Minimum elongation3.5%3.5%
Listed standardIS 14268:2022IS 14268:2022

See the product details for 12.9 mm LRPC strand coils and 15.2 mm LRPC strand coils.

These sizes should not be treated as interchangeable. Any proposed substitution needs approval from the responsible design or technical team before purchase or use.

2. Connect the order quantity to the production plan

Ask the production team for its planned strand requirement over the purchasing period. Keep confirmed production requirements separate from tentative work so that the supplier understands what is ready to order and what is only a forecast.

Useful information includes:

  • The approved strand size and specification.
  • Planned production dates.
  • Estimated material consumption.
  • Material already allocated to other jobs.
  • Any allowance approved by your team for cutting losses or contingency.

Use your own production records and approved calculations to determine quantities. A generic wastage percentage may not suit your process.

For a broader purchasing checklist, refer to the LRPC strand procurement guide.

3. Check usable stock before ordering

The total material physically present at a yard may differ from the quantity available for the next production run. Some coils may already be allocated to another project, awaiting inspection or held pending a quality decision.

A simple stock review can make this distinction clear:

Stock review for the next production run
Stock categoryWhat to record
Available stockMaterial cleared and available for the planned work
Allocated stockMaterial reserved for another production requirement
Material on holdStock awaiting inspection, documents or a decision
Confirmed incoming stockOrdered quantity and the supplier’s confirmed delivery schedule

Record the relevant coil or lot identifiers alongside quantities. This helps the team connect stock records with supporting documents.

Only count incoming material against the production plan after checking its expected arrival and allowing time for your receiving and inspection process.

4. Agree on delivery dates and unloading arrangements

Tell the supplier when the material is needed at the yard, rather than providing only a purchase-order date.

Include the delivery address, PIN code, receiving contact and any restrictions on vehicle access or unloading hours. Confirm who will arrange unloading and whether the necessary equipment will be available.

Wire Shoppe’s stated dispatch time is 1–2 days after order confirmation and receipt of advance payment. Dispatch time is different from arrival time: the expected delivery date should be confirmed for the destination and order.

If you need staggered deliveries, ask the supplier to confirm the quantities, dates and commercial terms for each dispatch. A forecast or quotation should not be treated as confirmation that future stock has been reserved.

5. Keep lot documents connected to the material

Before dispatch, confirm which documents your quality team requires and how they will be supplied.

At receipt, check that the material identification and relevant test-certificate details correspond. Keep these records accessible to the team responsible for inspection and release.

Technical sheets help buyers review product specifications, but they do not replace the lot-specific documents required by your project or quality process.

Visit the technical documents page for available reference material. For receiving checks, use the LRPC strand delivery checklist.

6. Review each delivery before repeating the order

A repeat order should include a quick review of the previous delivery. Check whether the specification, quantity, documents and delivery arrangements met the requirement.

Record any difference between forecast and actual consumption. Use that information to improve the next order quantity and timing.

If material arrives with damage, identification differences or missing documents, record the issue and follow your site’s inspection and acceptance procedure. Avoid assuming that a previous satisfactory delivery automatically clears the next lot.

7. Send a clear repeat-order enquiry

A concise enquiry can help the supplier prepare a relevant quotation. Include:

  • Product and approved specification.
  • Required quantity and unit of measurement.
  • Delivery location and PIN code.
  • Required arrival date or delivery schedule.
  • Documentation requirements.
  • Reference to the previous order, where relevant.

Ask for confirmation of availability, payment terms, freight arrangements and dispatch timing for the new order. Previous pricing or delivery arrangements should be reconfirmed.

Plan your next LRPC strand requirement

Share your approved strand specification, required quantity, delivery location and production timeline with Wire Shoppe P Ltd.

Request an LRPC strand quotation to discuss your next order.

Frequently asked questions

Which LRPC strand size should we order for precast production?

Use the size and specification approved for the precast element or project. Wire Shoppe lists Tata make 12.9 mm and 15.2 mm LRPC strand coils. Share the approved requirement when enquiring; a different diameter or breaking load should not be substituted without the responsible technical team’s approval.

Can we plan several deliveries against a production schedule?

You can share your expected quantities and required dates when requesting a quotation. Ask for written confirmation of the proposed dispatch schedule and terms for each delivery. Sharing a forecast alone does not confirm stock reservation, fixed future pricing or an agreed delivery commitment.

What information is needed for a repeat-order quotation?

Provide the product specification, quantity, delivery location, required date and documentation requirements. Include the previous purchase-order reference if useful, and highlight anything that has changed. Confirm availability and commercial terms for the new order rather than assuming the previous order’s conditions still apply.